Planning

MOQ and Lead Time by Process

Typical minimum order quantities and lead times for each process. Final dates are confirmed on the formal quotation.

MOQ and lead time at a glance

ProcessMinimum orderTypical lead time
3D printing (SLA, SLS, MJF)1 piece2–3 days
CNC prototypes1 piece3–5 days
CNC production1 piece5–10 days
Vacuum casting1 piece (up to about 500)5–7 days
Rapid tooling—About 15 days for the mold
Standard injection mold—25–35 days for the mold
Injection moldingTypically 500–1,000 parts per run15–35 days depending on quantity and finishing
Die castingQuoted per projectQuoted per project

What changes MOQ and lead time

Resin, color and changeover

Molding MOQ depends on material purchase quantities, the number of colors and set-up time.

Mold complexity

Slides, lifters, cavity count and steel grade drive the tooling schedule.

Finishing and assembly

Painting, plating, printing and sub-assembly add time and are scheduled with production.

Capacity

The workshop runs two shifts (about 18 hours a day); office hours are Mon–Sat 08:30–18:00 China time.

MOQ and lead time FAQ

Is there a minimum order for CNC machining?

No. CNC machining, 3D printing and vacuum casting start from 1 piece.

What is the MOQ for injection molding?

Typically 500–1,000 parts per run. For smaller quantities we recommend rapid tooling, vacuum casting or CNC machining.

Can you rush an order?

Rush service is available for prototypes. Tell us the date you need parts and we confirm what is achievable with the quote.

Get a schedule for your volume

Share annual quantity, colors and packaging · quote ≤24h on complete RFQ