T1 timeline

Sample Process: From Drawing to Approved Sample

Each step has a written output you can review, so problems are found on screen and in samples rather than in production.

Mold and sample timeline

Rapid tooling takes about 15 days and a standard mold 25–35 days. The schedule is confirmed before the order is placed.

1

RFQ package

3D and 2D files, resin, surface finish and volume estimate. NDA signed before file review.

2

DFM review

Free review of draft, wall thickness, gates, cooling and ejection, with mold-flow analysis where needed.

3

Mold build

Steel cutting, machining and EDM, with progress updates at agreed milestones.

4

T0 trial

Internal trial on the press; the tool is adjusted before samples leave the plant.

5

T1 samples

Samples ship with a dimensional report for your review.

6

Approval

After sign-off, the process window is fixed and production released.

Prototype samples before tooling

If the design is not frozen, validate it first with faster processes.

ProcessLead timeQuantity
3D printing (SLA, SLS, MJF)2–3 daysFrom 1 piece
CNC machined prototype3–5 daysFrom 1 piece
Vacuum casting5–7 days1–500 parts

Agree the sample inspection early

  • Dimensional focus: critical dimensions and datums to measure
  • Cosmetic class and inspection surfaces
  • Resin grade and color confirmation
  • Number of samples needed for your own testing

More detail: T1 sample lead time · rapid prototyping

Sample FAQ

How long until I receive T1 samples?

About 15 days for rapid tooling and 25–35 days for a standard mold, depending on complexity. The timeline is confirmed before you order.

Do samples come with an inspection report?

Yes. T1 samples ship with a dimensional report.

Can I get samples before paying for a production mold?

Yes. Prototypes by 3D printing, CNC machining or vacuum casting can validate the design first, from 1 piece.